Deciding, Quantitatively, Whether to Go Ahead(Also known as CBA and Benefit-Cost Analysis)
©
iStockphoto Do the benefits justify the cost? Imagine that you've recently taken on a new project, and your people are struggling to keep up with the increased workload. You are therefore considering whether to hire a new team member. Clearly, the benefits of hiring a new person need to significantly outweigh the associated costs. This is where Cost-Benefit Analysis is useful. Note:CBA is a quick and simple technique that you can use for non-critical financial decisions. Where decisions are mission-critical, or large sums of money are involved, other approaches – such as use of Net Present Values and Internal Rates of Return – are often more appropriate. About the ToolJules Dupuit, a French engineer and economist, introduced the concepts behind CBA in the 1840s. It became popular in the 1950s as a simple way of weighing up project costs and benefits, to determine whether to go ahead with a project. As its name suggests, Cost-Benefit Analysis involves adding up the benefits of a course of action, and then comparing these with the costs associated with it. The results of the analysis are often expressed as a payback period – this is the time it takes for benefits to repay costs. Many people who use it look for payback in less than a specific period – for example, three years. You can use the technique in a wide variety of situations. For example, when you are:
However, bear in mind that it is best for making quick and simple financial decisions. More robust approaches are commonly used for more complex, business-critical or high cost decisions. How to Use the ToolFollow these steps to do a Cost-Benefit Analysis. Step One: Brainstorm Costs and BenefitsFirst, take time to brainstorm all of the costs associated with the project, and make a list of these. Then, do the same for all of the benefits of the project. Can you think of any unexpected costs? And are there benefits that you may not initially have anticipated? When you come up with the costs and benefits, think about the lifetime of the project. What are the costs and benefits likely to be over time? Step Two: Assign a Monetary Value to the CostsCosts include the costs of physical resources needed, as well as the cost of the human effort involved in all phases of a project. Costs are often relatively easy to estimate (compared with revenues). It's important that you think about as many related costs as you can. For example, what will any training cost? Will there be a decrease in productivity while people are learning a new system or technology, and how much will this cost? Remember to think about costs that will continue to be incurred once the project is finished. For example, consider whether you will need additional staff, if your team will need ongoing training, or if you'll have increased overheads. Step Three: Assign a Monetary Value to the BenefitsThis step is less straightforward than step two! Firstly, it's often very difficult to predict revenues accurately, especially for new products. Secondly, along with the financial benefits that you anticipate, there are often intangible, or soft, benefits that are important outcomes of the project. For instance, what is the impact on the environment, employee satisfaction, or health and safety? What is the monetary value of that impact? As an example, is preserving an ancient monument worth $500,000, or is it worth $5,000,000 because of its historical importance? Or, what is the value of stress-free travel to work in the morning? Here, it's important to consult with other stakeholders and decide how you'll value these intangible items. Step Four: Compare Costs and BenefitsFinally, compare the value of your costs to the value of your benefits, and use this analysis to decide your course of action. To do this, calculate your total costs and your total benefits, and compare the two values to determine whether your benefits outweigh your costs. At this stage it's important to consider the payback time, to find out how long it will take for you to reach the break even point – the point in time at which the benefits have just repaid the costs. For simple examples, where the same benefits are received each period, you can calculate the payback period by dividing the projected total cost of the project by the projected total revenues: Total cost / total revenue (or benefits) = length of time (payback period). ExampleCustom Graphic Works has been operating for just over a year, and sales are exceeding targets. Currently, two designers are working full-time, and the owner is considering increasing capacity to meet demand. (This would involve leasing more space and hiring two new designers.) He decides to complete a Cost-Benefit Analysis to explore his choices. Assumptions
Costs
Benefits
He calculates the payback time as shown below: $139,750 / $305,500 = 0.46 of a year, or approximately 5.5 months. Subscribe to Our NewsletterReceive new career skills every week, plus get our latest offers and a free downloadable Personal Development Plan workbook. Read our Privacy Policy Inevitably, the estimates of the benefit are subjective, and there is a degree of uncertainty associated with the anticipated revenue increase. Despite this, the owner of Custom Graphic Works decides to go ahead with the expansion and hiring, given the extent to which the benefits outweigh the costs within the first year. Flaws of Cost-Benefit AnalysisCost-Benefit Analysis struggles as an approach where a project has cash flows that come in over a number of periods of time, particularly where returns vary from period to period. In these cases, use Net Present Value (NPV) and Internal Rate of Return (IRR) calculations together to evaluate the project, rather than using Cost-Benefit Analysis. (These also have the advantage of bringing "time value of money" into the calculation.) Also, the revenue that will be generated by a project can be very hard to predict, and the value that people place on intangible benefits can be very subjective. This can often make the assessment of possible revenues unreliable (this is a flaw in many approaches to financial evaluation). So, how realistic and objective are the benefit values used? Key PointsCost-benefit analysis is a relatively straightforward tool for deciding whether to pursue a project. To use the tool, first list all the anticipated costs associated with the project, and then estimate the benefits that you'll receive from it. Where benefits are received over time, work out the time it will take for the benefits to repay the costs. You can carry out an analysis using only financial costs and benefits. However, you may decide to include intangible items within the analysis. As you must estimate a value for these items, this inevitably brings more subjectivity into the process. Which of the following types of participant would likely be considered vulnerable by an institutional review board?The federal regulations require that IRBs give special consideration to protecting the welfare of particularly vulnerable subjects, such as children, prisoners, pregnant women, mentally disabled persons, or economically or educationally disadvantaged persons.
Which of the following types of participant would likely be considered vulnerable by an institutional review board quizlet?-the following types of subjects might be considered vulnerable: -children, handicapped, cardiac rehab patients, welfare recipients, prisoners, pregnant women, patients in a mental hospital, ect.
Which of the following is not one of the basic principles of ethical research with human subjects?The correct answer is d.
Potential harm should be avoided, or minimized to protect the participants, as well as debriefing the participants upon completion.
What is the group at a university that decides on the ethical merit of a research proposal?The IRB reviews the proposals before a project is submitted to a funding agency to determine if the research project follows the ethical principles and federal regulations for the protection of human subjects. The IRB has the authority to approve, disapprove or require modifications of these projects.
|