34.Air pressure must be in a tight range for the proper performance of aerosol airfresheners. Engineering specifications call for 50 psi of pressure with an uppertolerance of 55 psi and a lower tolerance of 45 psi. A sample from the previousweek's production had a mean of 51 psi and a standard deviation of 1.5 psi. What isthe capability of the process?35.

Get answer to your question and much more

Attribute data can be tracked on what type of control chart?36.

Get answer to your question and much more

Projects generally have all the following characteristics except37. Being an expert in information integration, project scope, time management, quality

Get answer to your question and much more

management, human resources, communications, risk, and procurement are beneficialskills for what member of a project management team?38. Which of the following relationships between cost, time, and scope is not realistic?

Get answer to your question and much more

39. Which of the following is not a project management tool?

Get answer to your question and much more

40. A network diagram is used to show what

Get answer to your question and much more

Get answer to your question and much more

41.Which is true about the critical path?42.

Get answer to your question and much more

The amount of leeway each activity has in its starting time and duration withoutdelaying the project43. Which of the following is not a time estimate used in PERT?

Get answer to your question and much more

Get answer to your question and much more

44.When computing the expected time for a project, which time estimate is weightedthe most?45. Which is not a general risk category for project management?

Get answer to your question and much more

Get answer to your question and much more

Project risk can be grouped into four categories. Which of the following is not one ofthe categories?47.The percentage of the project’s scope that will be affected by a problem defines

Get answer to your question and much more

which project risk classification?48.Which of the following is not a reason projects succeed?

Get answer to your question and much more

Get answer to your question and much more

An approach to reduce the amount of fluctuations in day-to-day resourcerequirements within an organization is

Get answer to your question and much more

Section 4- Project ManagementQuestions:1.Projects generally have all the following characteristics except:2.Being an expert in information integration, project scope, time

Get answer to your question and much more

management, quality management, human resources,communications, risk, and procurement are beneficial skills for whatmember of a project management team?

Get answer to your question and much more

3.Which of the following relationships between cost, time and scope isnot realistic?

Get answer to your question and much more

4.Which of the following is not a project management tool?

Get answer to your question and much more

5.A network diagram is used to show what?

Get answer to your question and much more

6.Which is true about the critical path?7.The amount of leeway each activity has in its starting time and

Get answer to your question and much more

duration without delaying the project.

Get answer to your question and much more

8.Which of the following is not a time estimate used in PERT?

Get answer to your question and much more

9.When computing the expected time for project, which time estimate isweighted the most?

Get answer to your question and much more

10. Which is not a general risk category for project management?

Get answer to your question and much more

11. Project risk can be grouped into four categories. Which of thefollowing is not one of the categories?

Get answer to your question and much more

12. The percentage of the project’s scope that will be affected by aproblem defines which project risk classification?

Get answer to your question and much more

13. Which of the following is not a reason projects succeed?14. An approach to reduce the amount of fluctuations in day-to-day

Get answer to your question and much more

resource requirements within an organization is:

Get answer to your question and much more

Which is one of the most distinctive features of a service?

Intangibility: Services are intangible and do not have a physical existence. Hence services cannot be touched, held, tasted or smelt. This is most defining feature of a service and that which primarily differentiates it from a product.

What are the two primary considerations in marketing strategy?

Any good marketing strategy has to take into consideration factors that are both internal and external. Internal factors include the marketing mix, performance analysis, budgetary constraints, etc. External factors are elements like customer experience, competitor analysis, the socio-economic environment, and so on.

Which of the following is are fundamental differences between services and manufacturing?

There are five main differences between service and manufacturing organizations: the tangibility of their output; production on demand or for inventory; customer-specific production; labor-intensive or automated operations; and the need for a physical production location.

Which term refers to a customer associating the quality of a product with the image of the company?