What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?

A theorem that determines the average number of items in queuing systems

What is Little’s Law?

Little’s Law is a theorem that determines the average number of items in a stationary queuing system, based on the average waiting time of an item within a system and the average number of items arriving at the system per unit of time.

What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?

The law provides a simple and intuitive approach for the assessment of the efficiency of queuing systems. The concept is hugely significant for business operations because it states that the number of items in the queuing system primarily depends on two key variables and is not affected by other factors, such as the distribution of the service or service order.

Almost any queuing system and even any sub-system (think about a single teller in a supermarket) can be assessed using the law. In addition, the theorem can be applied in different fields, from running a small coffee shop to the maintenance of the operations of a military airbase.

Our Math for Corporate Finance course demonstrates the foundational mathematics required for Financial Analysis and Corporate Finance.

Origin of Little’s Law

Massachusetts Institute of Technology (MIT) professor, John Little, developed Little’s Law in 1954. The initial publication of the law did not contain any proof of the theorem. However, in 1961, Little published proof that there is no queuing situation where the described relationship does not hold. Little later received recognition for his work in operations research.

Formula for Little’s Law

Mathematically, Little’s Law is expressed through the following equation:

What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?

Where:

L – the average number of items in a queuing system

λ – the average number of items arriving at the system per unit of time

W – the average waiting time an item spends in a queuing system

Example of Little’s Law

John owns a small coffee shop. He wants to know the average number of customers queuing in his coffee shop, to decide whether he needs to add more space to accommodate more customers. Currently, his queuing area can accommodate no more than eight people.

John measured that, on average, 40 customers arrive at his coffee shop every hour. He also determined that, on average, a customer spends around 6 minutes in his store (or 0.1 hours). Given these inputs, John can find the average number of customers queuing in his coffee shop by applying Little’s Law:

L  =  40 x 0.1  =  4 customers

Little’s Law shows that, on average, there are only four customers queuing in John’s coffee shop. Therefore, he does not need to create more space in the store to accommodate more queuing customers.

CFI is the official provider of the Financial Modeling and Valuation Analyst (FMVA)™ certification program, designed to transform anyone into a world-class financial analyst. To keep learning and developing your knowledge of financial analysis, we highly recommend the additional CFI resources below:

  • First-in, First-out (FIFO)
  • Inventory
  • Last-in, First-out (LIFO)
  • Lead Time

What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?

  • Home
  • My Books
  • Browse ▾

    • Recommendations
    • Choice Awards
    • Genres
    • Giveaways
    • New Releases
    • Lists
    • Explore
    • News & Interviews

    • Art
    • Biography
    • Business
    • Children's
    • Christian
    • Classics
    • Comics
    • Cookbooks
    • Ebooks
    • Fantasy
    • Fiction
    • Graphic Novels
    • Historical Fiction
    • History
    • Horror
    • Memoir
    • Music
    • Mystery
    • Nonfiction
    • Poetry
    • Psychology
    • Romance
    • Science
    • Science Fiction
    • Self Help
    • Sports
    • Thriller
    • Travel
    • Young Adult
    • More Genres

Showing 151-180 of 198

“If you consider the total time from the moment the material comes into the plant to the minute it goes out the door as part of a finished product, you can divide that time into four elements. One of them is setup, the time the part spends waiting for a resource, while the resource is preparing itself to work on the part. Another is process time, which is the amount of time the part spends being modified into a new, more valuable form. A third element is queue time, which is the time the part spends in line for a resource while the resource is busy working on something else ahead of it. The fourth element is wait time, which is the time the part waits, not for a resource, but for another part so they can be assembled together. As Jonah pointed out last night, setup and process are a small portion of the total elapsed time for any part. But queue and wait often consume large amounts of time—in fact, the majority of the elapsed total that the part spends inside the plant. For parts that are going through bottlenecks, queue is the dominant portion. The part is stuck in front of the bottleneck for a long time. For parts that are only going through non-bottlenecks, wait is dominant, because they are waiting in front of assembly for parts that are coming from the bottlenecks. Which means that in each case, the bottlenecks are what dictate this elapsed time. Which, in turn, means the bottlenecks dictate inventory as well as throughput.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“If we cut our batch sizes in half, then I guess that at any one time we’d have half the work-in-process on the floor. I guess that means we’d only need half the investment in work-in-process to keep the plant working. If we could work it out with our vendors, we could conceivably cut all our inventories in half, and by cutting our inventories in half, we reduce the amount of cash tied up at any one time, which eases the pressure on cash flow.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“I’ve been complaining about our problems with the six or seven capacity constraint resources, I raised all the red flags, I’ve gone as far as to demand that incoming orders be restricted. And now I see that I’ve created the problem with my own hands.” “Fill us in, Stacey,” I request. “You’re way ahead of us.” “Of course. You see, when do the green and red tags have an impact? Only when a work center has a queue, when the worker has to choose between two different jobs that are waiting; then he always works on the red tag first.” “So?” “The largest queues,” Stacey goes on, “are in front of the bottlenecks, but there the tags are irrelevant. The other place where we have relatively high queues is in front of the capacity constraint resources. These resources supply some parts to the bottlenecks, red-tag parts, but they work on many more greentag parts, parts that go to assembly not through the bottlenecks. Today they do the red-tag parts first. This naturally delays the arrival of the green parts to assembly. We catch it when it is pretty late, when holes are already evident in the assembly buffer. Then, and only then, we go and change the priorities at those work centers. Basically, we restore the importance of the green parts.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“I talked to Jonah last night.” “Did you tell him about our progress?” she asks. “Yes,” I say. “And he suggested we try what he called ‘the next logical step.’ ” I see her face take on a nervous grin. “What’s that?” “Cut our batch sizes in half on non-bottlenecks,” I say. Stacy takes a step back as she thinks about this. “But why?” she asks. I say with a smile, “Because in the end we’ll make more money.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“So what you’re telling us,” Bob cannot contain his surprise, “is that if you just eliminate the tags, it will be much better?” “Yes, that’s what I’m saying. If we eliminate the tags and we instruct the workers to work according to the sequence in which the parts arrive—first come, first done—the parts will be done in the right sequence, fewer holes will be created in the buffers, my people will not have to track where the material is stuck, and . . .” “And the foreman will not have to constantly reshuffle priorities.” Bob completes her sentence.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“And what happened to efficiencies? Well, they did fall initially as we began to withhold raw material from the floor, but not as much as we had been afraid they would—it turns out we were consuming excess inventory. But with the rate of shipments up dramatically, that excess has melted quickly. And now that we’re beginning to resume releases of materials to non-bottlenecks again, efficiencies are on their way back up. Donovan has even told me confidentially he thinks the real numbers in the future will be almost the same as before.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Once the somebody is already on the payroll, it doesn’t cost us any more to have him be idle. Whether somebody produces parts or waits a few minutes doesn’t increase our operating expense. But excess inventory . . . now that ties up a lot of money.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“If Ralph can determine a schedule for releasing red-tag materials based on the bottlenecks, he can also determine a schedule for final assembly. Once he knows when the bottleneck parts will reach final assembly, he can calculate backwards and determine the release of the non-bottleneck materials along each of their routes. In this way, the bottlenecks will be determining the release of all the materials in the plant.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Well, since we started keeping data on the bottlenecks, I’ve been noticing I’m able to predict several weeks in advance what each bottleneck will be working on at a particular time. See, as long as I know exactly what’s in queue, I just take the average setup and process times for each type of part, and I’m able to calculate when each batch should clear the bottleneck. Because we’re only dealing with one work center, with much less dependency, we can average the statistical fluctuations and get a better degree of accuracy.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“We all knew how important it was to make the bottlenecks work all the time.” Stacey starts at last to explain. “Remember, ‘An hour lost on the bottleneck is an hour lost for the entire plant.’ So, when I realized that the load on the bottlenecks was dropping, I issued orders for products to be on the shelf, in stock. Stupid, I know now, but at least at the moment our finished goods are balanced to roughly six weeks. No more of that awful situation where we hold mountains of some products and not even one single unit of others.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“If we can withhold materials for red parts, instead of pushing them out there as soon as the first non-bottleneck has nothing to do,” said Stacey, “the milling machines will then have time to work on the green parts. And the parts we’re missing will reach assembly with no problem.” Jonah nodded and said, “That’s right. What you have to do is find a way to release the material for the red parts according to the rate at which the bottlenecks need material—and strictly at that rate.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“IDENTIFY the system’s constraint(s). 2. Decide how to EXPLOIT the system’s constraint(s). 3. SUBORDINATE everything else to the above decision. 4. ELEVATE the system’s constraint(s). 5. WARNING!!!! If in the previous steps a constraint has been broken, go back to step 1, but do not allow INERTIA to cause a system’s constraint.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“I say, “So the bottom line is this: to give the robots more to do, we released more materials.” “Which, in turn, increased inventories,” says Stacey. “Which has increased our costs,” I add. “But the cost of those parts went down,” says Lou. “Did it?” I ask. “What about the added carrying cost of inventory? That’s operational expense. And if that went up, how could the cost of parts go down?”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“What happened was that even as throughput increased, we continued loading the plant with inventory as if we expected to keep all our workers fully activated. This increased the load dumped upon the milling machines and pushed them beyond their capacity. The first-priority, red-tagged parts were processed, but the green-tagged parts piled up. So not only did we get excess inventory at the NCX-10 and at heat-treat, but due to the volume of bottleneck parts, we clogged the flow at another work center and prevented non-bottleneck parts from reaching assembly.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Putting it precisely, activating a resource and utilizing a resource are not synonymous.” He explains that in both rules, “utilizing” a resource means making use of the resource in a way that moves the system toward the goal. “Activating” a resource is like pressing the ON switch of a machine; it runs whether or not there is any benefit to be derived from the work it’s doing. So, really, activating a non-bottleneck to its maximum is an act of maximum stupidity.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“All the changes that we made so far, all the sacred cows that we had to slaughter, had one thing in common, they all stem from cost accounting. Local efficiencies, optimum batch sizes, product cost, inventory evaluations, all came from the same source. I didn’t have much problem with it. As a controller I questioned cost accounting validity for a long time. Remember, it’s the invention of the beginning of the century when conditions were much different from today. As a matter of fact, I started to have a very good guideline; if it comes from cost accounting it must be wrong.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“A major constraint here in your system is this machine,” says Jonah. “When you make a non-bottleneck do more work than this machine, you are not increasing productivity. On the contrary, you are doing exactly the opposite. You are creating excess inventory, which is against the goal.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Whenever the constraint is broken it changes conditions to the extent that it is very dangerous to extrapolate from the past.” “As a matter of fact,” Stacey adds, “even the things that we put in place in order to elevate the constraint must be reexamined.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Stacey points out immediately that in no case does Y ever determine throughput for the system. Whenever it’s possible to activate Y above the level of X, doing so results only in excess inventory, not in greater throughput. “Yes, and if we follow that thought to a logical conclusion,” says Jonah, “we can form a simple rule which will be true in every case: the level of utilization of a non-bottleneck is not determined by its own potential, but by some other constraint in the system.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Sure, at first glance it looks as if we can use one hundred percent of Y, but think again.” “We can only use as much as the market demand can absorb,” I say. “Correct. By definition, Y has excess capacity,” says Jonah. “So if you work Y to the maximum, you once again get excess inventory. And this time you end up, not with excess work-in-process, but with excess finished goods. The constraint here is not in production. The constraint is marketing’s ability to sell.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Eighty percent of your products require at least one part from a bottleneck. What are you going to substitute for the bottleneck part that hasn’t shown up yet?” Bob scratches his head and says, “Oh, yeah . . . I forgot.” “So if we can’t assemble,” says Stacey, “we get piles of inventory again. Only this time the excess inventory doesn’t accumulate in front of a bottleneck; it stacks up in front of final assembly.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“With the bottlenecks more productive now, our throughput has gone up and our backlog is declining. But making the bottlenecks more productive has put more demand on the other work centers. If the demand on another work center has gone above one hundred percent, then we’ve created a new bottleneck.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“Dammit, what the hell is going on out there? I had assumed the parts that have to go through a bottleneck would reach assembly last. Is there a materials shortage on those green-tagged parts? Some kind of vendor problem?” I ask her. Stacey shakes her head. “No, I haven’t had any problems with purchasing. And none of the parts have any processing by outside contractors. The problem is definitely internal. That’s why I really think we have one or more new bottlenecks.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“The bottlenecks have spread.” “What do you mean ‘the bottlenecks have spread’?” I ask. “Is there a disease out there or something?” “No, what I mean is we have a new bottleneck—or maybe even more than one; I’m not sure yet.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement

“So you’re splitting and overlapping some batches,” I say. “Sure,” he says. “I know we’re not really supposed to do that, but you need the parts, right?” “Sure, no problem. You’re still doing the treating according to the priority system?” I ask. “Oh, yeah,” he says. “Come here. Let me show you.” Mike leads me past the control console for the furnaces to a worn old battleship of a desk. He finds the computer print-out for the week’s most important overdue orders. “See, look at number 22,” he says pointing to it. “We need fifty of the high stress RB-dash-11’s. They get treated at a 1200– degree temperature cycle. But fifty of them won’t fill up the furnace. So we look down and what do we see here but item number 31, which calls for 300 fitted retaining rings. Those also take a 1200–degree cycle.” “So you’ll fill up the furnace with as many of the retaining rings after you’ve loaded the fifty of the first item,” I say.”
Eliyahu M. Goldratt, The Goal: A Process of Ongoing Improvement


All Quotes | Add A Quote

What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?
Critical Chain
3,469 ratings
Open Preview

See a Problem?

We’d love your help. Let us know what’s wrong with this preview of Critical Chain by Eliyahu M. Goldratt.

Thanks for telling us about the problem.

What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?
It's Not Luck
2,617 ratings
Open Preview

See a Problem?

We’d love your help. Let us know what’s wrong with this preview of It's Not Luck by Eliyahu M. Goldratt.

Thanks for telling us about the problem.

What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?
Theory of Constraints
900 ratings
Open Preview

See a Problem?

We’d love your help. Let us know what’s wrong with this preview of Theory of Constraints by Eliyahu M. Goldratt.

Thanks for telling us about the problem.


Welcome back. Just a moment while we sign you in to your Goodreads account.

What is the term used for the time a unit spends being worked on together with the time it spends waiting in one or more queues?

Is the time that the unit spends actually being worked on together with the time spent waiting in a queue?

Throughput rate of a production process is the amount of time a unit spends actually being worked on.

Which of the following is the best definition for throughput time?

Throughput time is the actual time taken for a product to be manufactured. This is the duration of time required for the production process as well as the other time periods involved in converting raw materials into finished goods.

Which of the following refers to the fixed timing of the movement of items through the process?

Pacing in production processes refers to the fixed timing of the movement of items through the process. True. When we use a make-to-stock production process, we control our production based on a desired amount of finished goods inventory.

Which of the following best describes the term cycle time quizlet?

Which of the following best describes the term "cycle time"? The cycle time of a repetitive process is the average time between completions of successive units.