Reducing the impact of a risk event by reducing the possibility of its occurrence is

Reducing the impact of a risk event by reducing the possibility of its occurrence is

Project Risk Terms and Definitions

Terms and Definitions used regularly in construction projects and defined in PMI PMBOK

A project risk is a potential source of deviation from the project plan. Project risks can have a negative or positive impact on the project. Project risks that are negative are called threats. Project risks that are positive are called opportunities.Non-critical risks should be documented. They should be revisited and reviewed regularly.Risks are identified in all phases.Work-around refers to how to handle risks that have occurred but are not part of risk response plan. This happens in risk monitoring and control phase.


  • Amount at Stake: The extent of adverse consequences which could occur to the project. (Also referred to as risk impact).

  • Business Risk: The inherent chances for both profit and loss associated with a particular endeavor.

  • Contingency Planning: The development of a management plan that identifies alternative strategies to be used to ensure project success if specified risk events occur.

  • Contingency Reserve: A separately planned quantity used to allow for future situations which may be planned for only in part (“known unknowns”). Contingency reserves are intended to reduce the impact of missing cost or schedule objectives. Contingency reserves are normally included in the project’s cost and schedule baselines.

  • Deflection: The act of transferring all or part of a risk to another party, usually by some form of contract.

  • Expected Monetary Value: The product of an event’s probability of occurrence and the gain or loss that will result. For example, if there is a 50% probability it will rain, and rain will result in a $100 loss, the expected monetary value of the rain event is $50 (.5 * $100).

  • Impact Analysis: The mathematical examination of the nature of individual risks on the project, as well as potential arrangements of interdependent risks. It includes the quantification of their respective impact severity, probability, and sensitivity to changes in related project variables, including the project life cycle.

  • Insurable Risk: A particular type of risk which can be covered by an insurance policy. Also referred to as a pure risk.

  • Management Reserve: A separately planned quantity used to allow for future situations which are impossible to predict. (“unknown unknowns”) Management reserves are intended to reduce the risk of missing cost or schedule objectives. Use of management reserves requires a change to the project’s cost baseline.

  • Mitigation: Taking steps to lessen risk by lowering the probability of a risk event’s occurrence or reducing its effect should it occur.
  • Monte Carlo Analysis: A schedule risk assessment technique that performs a project simulation many times in order to calculate a distribution of likely results.

  • Opportunities: As related to risk, positive outcomes of risk.

  • Project Risk Management: Includes the processes concerned with identifying, analyzing, and responding to project risk.

  • Risk Event: A discrete occurrence that may affect the project for better or worse.

  • Risk Identification: Determining which risk events are likely to affect the project.

  • Risk Management Plan: A subsidiary element of the overall project plan which documents the procedures that will be used to manage risk throughout the project. Also covers who is responsible for managing various risk areas; how contingency plans will be implemented, and how reserves will be allocated.

  • Risk Quantification: Evaluating the probability of risk event occurrence and effect.

  • Risk Response Control: Responding to changes in risk over the course of the project.

  • Risk Response Development: Defining enhancement steps for opportunities and mitigation steps for threats.

  • Threats: As related to risk, negative outcomes of risk.

  • Total Certainty: All information is known.

  • Total Uncertainty: No information is available and nothing is known. By definition, total uncertainty cannot be envisaged.
  • Uncertainty: The possibility that events may occur which will impact the project either favorably or unfavorably. Uncertainty gives rise to both opportunity and risk.

  • Workaround: A response to a negative risk event. Distinguished from contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.

  • Avoidance: Changing the project plan to eliminate the risk and protect the project objectives.

  • Transference: Shift the consequence of the risk and ownership to a third party. (E.g. insurance)

  • Mitigation: To reduce the probability/impact of a risk to an acceptable threshold. (E.g. prototype).

  • Exploit: This strategy may be selected for risks with positive impacts where the organization wishes to ensure that the opportunity is realized. This strategy seeks to eliminate the uncertainty associated with a particular upside risk by making the opportunity definitely happen. Directly exploiting responses include assigning more talented resources to the project to reduce the time to completion

  • Share: Sharing a positive risk involves allocating ownership to a third party who is best able to capture the opportunity for the benefit of the project. Examples of sharing actions include forming risk-sharing partnerships, teams, special-purpose companies, or joint ventures.

  • Enhance: This strategy modifies the .size. of an opportunity by increasing probability and/or positive impacts, and by identifying and maximizing key drivers of these positive-impact risks

Reducing the impact of a risk event by reducing the possibility of its occurrence is

Hany Ismael is the founder and CEO of Planning Engineer Est. in Egypt. He has started his career back in 2003 as a site engineer, technical office engineer, planning engineer, planning manager, and finally planning department manager where he has been involved in several mega construction projects in Egypt and Saudi Arabia. In 2016, he established his own company in Egypt “Planning Engineer Est.” Hany gained his MSc degree in project management from Liverpool University-UK 2013-2016, PMP certified from PMI-USA 2010, and BSc Civil Engineer Tanta University-Egypt 2003. Hany provided more than 3,500 hours of planning and project management training on his website planningengineer.net, YouTube channel, and offline courses since 2011. He enjoys teaching project management in simple and practical way, and he developed several planning tools, techniques and courses.

Next post

PROJECT CLOSE-OUT Template

February 3, 2014

Which risk strategy reduces the impact of a risk event by reducing the probability of its occurance?

Mitigate – act to reduce the probability of occurrence or the impact of the risk. An example of this is choosing a different supplier. Accept – acknowledge the risk, but do not take any action unless the risk occurs. An example of this is documenting the risk and putting aside funds in case the risk occurs.

What is risk mitigation?

Risk mitigation is the process of planning for disasters and having a way to lessen negative impacts. Although the principle of risk mitigation is to prepare a business for all potential risks, a proper risk mitigation plan will weigh the impact of each risk and prioritize planning around that impact.

What are 3 types of risk mitigating controls?

There are four common risk mitigation strategies. These typically include avoidance, reduction, transference, and acceptance.

What is risk reduction strategy?

Risk reduction definition: A risk becomes less severe through actions taken to prevent or minimise its impact. Risk reduction is a common strategy when it comes to risk treatment. It is sometimes known as lowering risk.