Which of the following statements is true about a critical path?
Project managers’ objectives include:
The advantage(s) of the network method over the Gantt chart is (are) that:
A network-based project scheduling method that requires three time estimates for eachactivity
is:PERTCPMGantt chartAll of the above
Project managers’ work
includes:
"Slack" refers to the difference between:
The information calculated from the forward and backward pass can be used for:
A forward pass is required while computing the early start and early finish times of
activities.TrueFalse
Critical path method (CPM) network scheduling assumes a second order (non-linear) time-cost tradeoff exists.
PERT assumes that the statistical variation in total project completion times can be computedby adding the standard deviations along the critical path.
Newly uploaded documents
Question - 104Which of the following statements is true regarding Critical Path?A. There can be more than one Critical Path in a Schedule Network DiagramB. Critical Paths generally always have negative
floatC. Activities on Critical Path have positive floatD. Critical Path has duration less than the non critical paths.A is the correct answer.The correct answer is Option A .Generally activities on Critical Path have Zerofloat.Critical Path is the one which has the longest duration - so options B,C and D
are notcorrect.You can always have more than one Critical Path in a project.
Question - 105Your company policy allows accepting gifts from customers within certain limit. Yourcustomer is giving you a gift which is beyond the limit of your company policy. You havegiven a gift to the customer's representative already which has similar in
value. Whatshould you do?
Question -
106You are responsible for a project with high risks particularly during the early phases -your sponsor has asked for performance reports on a monthly basis. At the end of the firstmonth you report a CPI greater than 1 and also the SPI greater than 1. What would thismean
?
Question - 107You are the project manager of a software project. Your team member want to make
technical changes to an activity which will add more time to that activity. What should youdo ?
A. The critical path technique is the same as PERT. B. It allows for looping and branching. C. It should never be compressed. D. It's the duration of all tasks with zero float.
More Questions Like This
[Skip Breadcrumb Navigation]
Home
|
| Chapter 8
|
| Self-Test Questions
|
| Multiple Choice
|
This activity contains 14 questions.
|
|
|
|
|
Consider the following activities (times in weeks):
Act.
| IP
| Mean
| CT
|
| C/W
| A
| −
| 2
| 2
|
| N/A
| B
| A
| 4
| 3
|
| $800
| C
| A
| 3
| 2
|
| $700
| D
| B, C
| 5
| 3
|
| $750
| E
| A
| 2
| 1
|
| $400
| F
| E
| 3
| 3
|
| N/A
| G
| D, F
| 5
| 4
|
| $1 000
|
IP = Immediate predecessor. CT = Min. completion time with max crash. C/W = Cost/week to reduce completion time. The latest start time for activity D is:
|
|
|
|
|
|
|
|
|
|
|
|
|
| Refer to Question #1. If the manager does not want to start activity A immediately, how long could he wait before starting this activity and still meet a deadline of 20 weeks?
|
|
|
|
|
|
|
|
|
|
|
|
|
| Refer to Question #1. Which of the following is the strategy to reduce the project to 12 weeks at a minimum cost?
|
|
|
|
|
|
|
|
|
|
|
|
|
| The latest finish time for an activity:
|
|
|
|
|
|
|
|
|
|
|
|
|
| Which of the following statements is true?
|
|
|
|
|
|
|
|
|
|
|
|
|
| An expected project completion time follows a normal distribution with a mean of 21 days and a standard deviation of 4 days. What is the probability that the project will be completed in a time between 22 to 25 days inclusive?
|
|
|
|
|
|
|
|
|
|
|
|
|
| Which of the following statements is true?
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Act.
| IP
|
|
| A
| −
|
| B
| −
|
| C
| A, B
|
| D
| A, C
|
Based on the list of activities above which of the following can be said?
|
|
|
|
|
|
|
|
|
|
|
|
|
| Which of the following can shorten the duration of an activity or project?
|
|
|
|
|
|
|
|
|
|
|
|
|
| The critical path in a network of activities:
|
|
|
|
|
|
|
|
|
|
|
|
|
| The Gantt Chart is used to:
|
|
|
|
|
|
|
|
|
|
|
|
|
| Which of the following statements is true?
|
|
|
|
|
|
|
|
|
|
|
|
|
| The immediate predecessors of any node in a project network drawn as a AON diagram :
|
|
|
|
|
|
|
|
|
|
|
|
|
| The standard deviation for a PERT diagram is calculated by:
|
|
|
|
|
|
|
|
|
Answer choices in this exercise appear in a different order each time the page is loaded.
Which of the following statements are true about a critical path?
Statement I & IV: True
The critical path is the sequence of critical activities that represents the longest path through a project, which determines the shortest possible project duration, if any one activity on critical path delays, it will impact the project completion date.
Which of the following statements is true regarding critical path there can be more than one critical path in a schedule network diagram?
Answer is option a - There can be more than one Critical Path in a Schedule Network Diagram. Generally activities on Critical Path have Zero float.
Which of the following statements regarding CPM network is true?
Which of the following statements regarding CPM is true? All activities on the critical path have their LS equal to the maximum EF of all immediate predecessors.
Which of the following is not true for a critical path?
It is calculated only on the longest path of the project schedule. It's the amount of time an activity can be delayed without delaying the project completion date. Which of the following is not true for critical path tasks? A: The early start date is not same as the late start date.